CIVIL ENGINEER

Soletanche Bachy Cimas-Geofundaciones Vinci Group Colombia

Leading the excavation team of 6 floors underground of a shopping center.

Planning the excavation of 326000m3 in open sky in an area of 16000m2

Planning and execution of the different ways to increase daily excavation volumes in urban areas 3D design of the excavation and how it would be implemented

Coordinator of the entire area belonging to excavation

Plan and coordinate the daily volume of trucks double traction and verification of the environmental part by land movement issues.

Achievements:

  • It was possible to increase the daily volume excavated to 4300m3 in the maximum curve well above the expected average.

  • By increasing the daily volume excavated, it was possible to recover the time that had been lost in another part of the contract.

  • By having a coherent planning and strategically determined load sites, the load is optimized by reducing the loading time and waiting to increase the daily trips of each dump truck which results in a gain of time and money.